Tools · Planning Approval Times

Planning permission in East Staffordshire

The decisions this council published on its planning register over the last 24 months, as held in our planning data: 1,371 applications decided, 93% approved. Data as of 2026-07-17.

Median decision time84 daysNoticeably slower than the national median of 56 days.
Approval rate93%Across all application types we hold: 1,271 approved of 1,371 decided.
Decided within 8 weeks30%1 in 10 waited longer than 233 days.

No withdrawals appear in the register data we hold for this authority.

By application type

Application typeDecidedApprovedMedian days
Full applications55790% (502)112
Tree works25595% (242)42
Discharge of conditions20398% (198)75
Outline applications16788% (147)55
Amendments7492% (68)87
Listed building and heritage7099% (69)118

The headline approval rate blends every type above, so read the row for the work you have in mind: tree works and condition discharges approve far more readily than full applications.

Nearby authorities

AuthorityDecidedApprovedMedian days
South Derbyshire1,18295%62
Lichfield1,55682%56
Derby49289%55
Cannock Chase75490%55

The official decision periods

England

The statutory time limits are 8 weeks for most applications, 13 weeks for major development and 16 weeks where an Environmental Impact Assessment applies, under article 34 of the Development Management Procedure Order 2015. Government policy adds that no application should spend more than a year with decision makers, including any appeal.

GOV.UK: Determining a planning application (MHCLG guidance) (opens in new tab)
Scotland

Planning authorities aim to decide local developments within 2 months and major developments within 4 months. If the decision takes longer, you can appeal.

mygov.scot: Planning permission, what happens next (opens in new tab)
Wales

The determination period is 8 weeks from the date the local planning authority received a valid application, under article 22 of the Development Management Procedure (Wales) Order 2012.

Town and Country Planning (Development Management Procedure) (Wales) Order 2012, article 22 (opens in new tab)
Northern Ireland

The council should decide your application within 8 weeks, though large or complex applications can take longer. If it is not determined within 8 weeks you can appeal to the Planning Appeals Commission.

nidirect: Making a planning decision (opens in new tab)

What each number means

Decisions

Approved plus refused decisions published on the council's planning register in the period shown. It counts what the register we read published, which can be less than everything the council handled.

Approval rate

The share of decided applications that were approved. Withdrawn applications sit outside this number: withdrawing is the applicant's act, not the council's decision.

Median decision time

The middle application, measured in days from the date the register says the council received it to the date it decided it. Half were faster, half slower. Councils and applicants can lawfully agree more time, so elapsed days beyond a target are not automatically a breach of it.

Decided within 8 weeks

The share of dated decisions made within 56 days of the received date on the register. 8 weeks is the decision period most standard applications start with; agreed extensions can lawfully move it.

Withdrawn

Applications the applicant withdrew before a decision. Shown separately and never counted in the approval rate.

Planning a project here?

Check whether you need planning permission at all, see approval odds by project type, or find architects with a real approval track record. Compare all authorities.

Common questions

How long does planning permission take in East Staffordshire?

Across the 1,371 dated decisions we hold from the last 24 months, the median application in East Staffordshire was decided in 84 days, and 1 in 10 waited longer than 233 days. 30% were decided within 8 weeks of the received date on the register. Noticeably slower than the national median of 56 days.

What share of planning applications does East Staffordshire approve?

93% of the 1,371 decided applications we hold were approved, across all application types on the register. For full applications alone it is 90% (502 of 557). Withdrawn applications sit outside these numbers.

Do these figures match the council's official statistics?

Not exactly, and they are not meant to. These figures are computed from the planning register entries we hold for each council, refreshed continuously from the public registers. They describe published register data, not the council's official performance statistics, and coverage per council can differ from the register's own totals. Always confirm requirements for your own project with your council before applying. Official statistics also count decisions made within an agreed extension of time as on time, so our elapsed-day figures can read slower than the official measure.

These figures are computed from the planning register entries we hold for each council, refreshed continuously from the public registers. They describe published register data, not the council's official performance statistics, and coverage per council can differ from the register's own totals. Always confirm requirements for your own project with your council before applying.